Sunday, May 21, 2017

Gable ends are finished and primed for paint.



Upper fascia board is done also, I started priming for paint on both upper & lower fascias:


House wrap stapled onto the new back wall and ready for siding:

And finally we started shingling:



Monday, May 8, 2017

Rob managed to dodge a few rain showers and get plywood sheathing on the gable ends.

He also sistered a few of the compromised rafters on the main roof and began installing a new fascia board so we have a place to mount gutters on the house.


P.S.  I got the siding and the shingles!
  

Sunday, May 7, 2017

It has been raining all week at the house, so progress is minimal.  Today my wife Robin came out to the house and helped me fill the dumpster by cleaning out the remaining furniture and the piano which was in the back half of the living room.

I got a before photo for contrast:

And after: