This past Sunday, Rob and I removed/burned all of the debris and wood from the garage demo. We filled about half of the dumpster, which is good because we have room leftover for the debris from the dining room wall which will be torn down this coming week.

Once there was no longer any evidence that a garage had ever been there, we moved on to the kitchen floor.   We installed new floor joists which were attached via joist hangars to the new
quadruple 2 X 10 beam that we installed the summer before last.

On the other end the joists rest on the new poured concrete foundation.  We started putting down the new 3/4" tongue & groove subfloor,  but the batteries in the camera died. I'll try to get photos next week.

The first Joist installed:

Yes I know, the wainscoting is shot. It will be replaced after the floor is done.